Water supply engineering.
A total of 11,042m of water supply was completed, accounting for about 85.2% of the water supply pipe work.
The CZ17 section is under construction for the water supply pipe.
West Island electric facilities relocation down to the beautification project construction.
Middle One Lane is laying pipe
New Village Road piped into homes.